    Estimation is hard and the easy path sometimes a little too tempting.

    Introduction

    The ability to estimate something is a core engineering skill. In software estimation is mostly about how long something will take to complete. I know lots of developers say they are terrible at estimation and will do anything to avoid giving a number. I think a lot of this has to do with our desire to be correct all the time but refusing to estimate isn’t helpful; you just need to accept that sometimes your estimates may not be accurate.

    Relative vs Absolute Sizing

    Humans in general are not great at working out the absolute size of something whether it be the length of a stick in meters or a task in hours. A good example of this is - quickly tell me how many characters are in the quote below?

    #############################

    Its quite hard to tell quickly by not counting individual characters. I tried by halving the string and then again and again until I could easily count 4 then multiplied by the segments I divided. This was a quick estimate of 8x4=32. The actual string length is 29 so I’m out by 3, not too bad.

    What humans are very very good at is estimating the relative size to something else. For example, is the second string longer, shorter or the same size as the previous one?

    ##############################

    What about this one?

    ############################

    Even though they are not right next to each other I’m sure you found it easy enough to guess they are longer and shorter respectively, even if its only by one character.

    When it comes to story estimation, we find it much easier to estimate by comparing to another, similar story and this is where planning poker often fails.

    Planning Poker

    I’m sure everyone knows how planning poker is supposed to work. Briefly its a little like this:

    1. Product Owner gives an overview of the story to be estimated
    2. The team ask questions to clarify assumptions and risks
    3. Each team member picks a card to represent the estimate for the story (commonly fibonacci story points)
    4. Everyone turns over their card
    5. The highest and lowest card holders get an opportunity to justify their position
    6. Repeat the card picking and justification until a consensus is formed

    There is even a pretty good extension for Azure DevOps to do all this remotely.

    This should be a good way of estimating as it depends on the wisdom of crowds to come to a consensus. My issue is that by default this is an absolute estimation method. Even worse, its an absolute estimate of a non-specific measure - story points.

    The part that is missing from most planning poker sessions is a menu of stories for comparison. This is especially true at the start of a project and the shear number of stories that need estimation create more temptation to take shortcuts.

    An Alternative

    My preferred method is to estimate all stories in one go by arranging them relative to each other. This is known as Affinity Estimation.

    The first stage to to add a bunch of cards to a big board and then, one-by-one, align them based on their relative complexity. You have to be careful to take input from everyone and ensure decisions are not biased by others. The same level of justification takes place over positioning. At no point do you assign an absolute value.

    Initial sorting

    If a story isn’t ready or its not possible to estimate I colour the card red and move it away for later refinement and splitting.

    You can put all the stories in a long line and just play higher or lower until the complete list is in relative size order but I find its easier to roughly group items and only place them in new columns when they are obviously bigger or smaller.

    Once you have a rough grouping its time to make some decisions over the items not obviously in one column or another.

    Bucketing

    Finally, check that each column represents stories that are approximately twice as big as the previous column. Only then can you assign your story point values.

    Assigning values

    This leaves you with a final block of estimations to paste back into Azure DevOps.

    Final estimations

    Don’t throw this board away. When you come to estimate the next bunch of stories if you add them to this board you already have a ready made set of reference stories. As it grows bigger you might want to prune it and possible remove any that ended up not being representative of the effort assigned originally.

    These reference stories can also be the basis for relative planning poker sessions in the future.

    Summary

    Whilst I’m a fan of #NoEstimates and Lean methods which drastically reduce the important of estimating, we all have a responsibility for estimating our work. Planning Poker isn’t the only game in town and its often abused so why not consider alternate ways of sizing your stories. Maybe try White Elephant Sizing once in a while too?

    Photo by Michał Parzuchowski on Unsplash

    This entry was posted in agile  and tagged #estimation #planning poker #opinion  on .
    Discuss this on Twitter or LinkedIn
  • Woman placing sticky notes on wall.

    Right now I’m reading “Agile Data Warehousing Project Management: Business Intelligence Systems Using Scrum” which I can heartily recommend. This article is about one quote in particular:

    Unfortunately, tracking actual hours spent on the individual tasks is ineffective, aims at the wrong objectives, and drowns the developers in detail while undermining agile’s pillar of self-organization that is so crucial to a team’s velocity. Tracking actuals should be strongly discouraged.

    I would go one step further and say tracking actuals can end up having a negative effect on your scrum project. Before I get into why its worth pointing out that for short periods of time it can be useful particularly if you need to gather data on where you are spending your time (see the second point below). Once you have the data though - stop recording.

    So why is tracking actuals so counterproductive? Primarily because it subverts the iterative estimation method.

    One of the key activities in a scrum process is to update the remaining time estimate every day. From this estimate a burn down is calculated and the burn down is then used to monitor and adjust the sprint in order to deliver.

    Consider what happens when scrum team members are logging the amount of time they worked on a task. Simple maths tells the remaining time is the current estimate minus the hours worked so there is a temptation to skip the re-estimating step. As a result a sprint burns down at a constant rate (ignoring task completion as a backup progress indicator) and inevitably it is not until the end of the sprint that underestimation is discovered; too late to do anything about it.

    This second point can be good or bad depending on management and team culture - if you log time correctly and in detail you will know where you are spending time including interruptions, meetings, etc. There are two types of response from the team:

    1. Look at all this waste activity we are doing - how can we remove it and spend more time on value add work?
    2. How can I possibly deliver on my sprint commitments - look at the other work I had to do during the sprint.

    Obviously you want the first response.

    Finally, overshooting sprints is something to be avoided but often there are additional constraints on time logging that cause you to miss estimate future sprints as well. I know of many organisations where team members are required to log a fixed number of hours a day; no more, no less. You can imagine the havoc this causes - if you work 5 or 15 hours during one day on a task but have to log 8 then you create an inaccurate data set from which to base future sprint planning on.

    Photo by Jason Goodman on Unsplash

    This entry was posted in agile  and tagged #estimation #scrum  on .